First Day
1. Make sure equipment is turned off.
2. Drain pool.
3. Drill holes into pool floor to level pressure.
4. If not replacing tile or coping.
Cut and chip underneath tile, pipes,lights etc.
5. Acid Wash .
6. Check for hollow and rotten areas and
remove. Check for open cracks on plaster
and fill in.
7. Apply Bond Kote to bond new plaster.
Second Day
1. Install toe tile on steps and benches.
(Optional)
2. Apply 2 coats of plaster.
3. Acid wash plaster.
( If required for particular material.)
4. Begin filling pool.
Brushing and proper Start Up procedures should begin as soon as water reaches water line tile.